The Town of Rolesville continues to work to complete work at the intersection of Main & Young Streets. See below for highlights: Once the … [Read more...] about Main & Young Streets Intersection Upgrades Continue
Travel on Main St. Through Young & Main Intersection Now OPEN!
Main Street though the Young & Main Intersection is now open in its short-term configuration. While work continues on the Main Street Project to … [Read more...] about Travel on Main St. Through Young & Main Intersection Now OPEN!
Project Intersection Closure
Based on the original project schedule, the Young Street and Main Street intersection was scheduled to be reopened by September 15th, 2024. Due … [Read more...] about Project Intersection Closure
Work Begins on ADA Ramp Improvements Section
The contractor began work updating curb ramps and sidewalks between Southtown Circle and School Street to current ADA standards. This will mean … [Read more...] about Work Begins on ADA Ramp Improvements Section